How Much Diesel Does a Data Center Store?

By Joel Yonkman

At about 7:00 p.m. on July 10, 2024, a lightning arrester failed on a 230 kV transmission line in the Eastern Interconnection. Voltage across a dense cluster of Northern Virginia data centers dipped repeatedly over the next minute, and roughly 1,500 megawatts of data center load moved off the grid and onto backup power. About 1,260 megawatts of it did not come back for hours (NERC Incident Review, Jan. 8, 2025).

The backup systems did exactly what they were built to do. For a host community, the more useful question is what made that possible: generator yards and large volumes of diesel fuel kept on site, often next to neighborhoods, schools and water plants. In our work with fire departments and county emergency managers, fuel storage is one of the hazards that gets the least attention during site plan review, and one of the easiest to settle early.

How much diesel does a data center keep on site?

There is no single number, because fuel is sized to generator capacity and to how long the owner wants to run without a delivery. Three reference points help.

  • Industry minimum. The Uptime Institute Tier Standard calls for at least 12 hours of on-site fuel at the design load for every Tier rating (Build, Nov. 18, 2026).

  • Common practice. Many large operators specify 48 to 96 hours of fuel, backed by resupply contracts (Build, Nov. 18, 2026).

  • The life-safety standard. NFPA 110 assigns emergency power systems a Class, which is the number of hours the system must run at rated load without refueling. Class X is a duration set by the code or the user, usually 48 to 96 hours (Consulting-Specifying Engineer).

The volumes add up quickly. One industry estimate puts 72 hours of fuel at about 5,688 usable gallons per megawatt of generator capacity at 75 percent load (Build). By that figure, a campus with 40 megawatts of generators planning for three days would hold more than 225,000 gallons. Virginia alone has about 9,000 backup generators, roughly 4,700 of them in Loudoun County (Virginia Mercury, Dec. 16, 2025).

What the codes and federal rules already require

Much of the framework exists. The gap is usually that no one has put the pieces in front of the fire chief and the emergency manager at the same time.

Fire code limits on fuel inside buildings

The International Fire Code limits fuel oil stored inside a building. As adopted in Oregon and applied by Portland Fire & Rescue, the aggregate of all tanks inside a building is capped at 660 gallons except for protected tanks, with exceptions allowing up to 3,000 gallons (Portland Fire & Rescue generator tank reference sheet, IFC/OFC 603.3.2.1). Most data center fuel therefore sits outdoors, in generator belly tanks and bulk tanks, where setbacks, containment, vents, fill points and apparatus access all matter. The edition your jurisdiction has adopted, and any local amendments, control.

Level 1 versus Level 2 power

NFPA 110 separates Level 1 systems, where failure could cost lives (egress lighting, fire alarm, fire pumps), from Level 2 systems, where failure could hamper rescue or firefighting (Consulting-Specifying Engineer). Most of a data center's generator capacity serves servers and cooling, not life safety. The fire department should know which generators feed the fire pump and alarm system and which do not.

Spill prevention plans

A facility with more than 1,320 U.S. gallons of aboveground oil storage, counting containers of 55 gallons or more, falls under EPA's Spill Prevention, Control, and Countermeasure rule and must prepare and implement a written SPCC Plan (40 CFR 112.1 and 112.3).

Tier II reporting to the fire department

Diesel fuel triggers EPCRA Tier II reporting at 10,000 pounds, about 1,430 gallons, with reports due March 1 each year (Florida Division of Emergency Management). Tier II reports go to the state emergency response commission, the local emergency planning committee and the local fire department (EPA). If your department has never seen one from a data center in its district, that is worth asking about.

Other fire services are moving

Fire and Rescue NSW in Australia issued a position in June 2026 on detached structures with vertically stacked diesel generators or tanks at data centres. It found their fire load beyond what is typical for the class of structure they are often approved under and expects fire separation, suppression and firefighting equipment proportionate to the risk (FRNSW position statement, June 2026). US jurisdictions can ask the same questions without waiting for a code change.

Seven questions to settle before the site plan

  • Total fuel at full build-out. Gallons per building, per generator yard and campus-wide, not just phase one.

  • Tank types and locations. Belly tanks, day tanks and bulk storage; protected tanks; secondary containment; where a spill would drain.

  • Generator yard layout. Separation between units and from buildings, apparatus access on at least two sides, hydrant spacing and water supply, and whether foam is needed.

  • Refueling during a long outage. Who delivers, how many trucks a day, which route, and whether those contracts compete with the hospital, the water plant and the county's own generators for the same supplier.

  • Testing and notification. The generator test schedule, and a standing notice to dispatch so smoke and noise calls during tests are not run as structure fires.

  • Documents to the fire department. Copies of the SPCC Plan, Tier II reports, site plans with shutoffs and an emergency contact list that works at 2 a.m.

  • Combined hazards. How fuel storage relates to battery rooms and the electrical yard. Our earlier piece on data center battery fires covers the battery side.

Fuel is a community resilience question too

A regional outage is exactly when a data center will draw on its fuel, and exactly when the county needs fuel for shelters, lift stations and emergency vehicles. Emergency managers should know how much fuel sits within the county, who has delivery priority and whether any of it could support critical facilities under a mutual agreement. These are planning conversations, not enforcement actions, and owners are usually willing to have them.

Get in early

The best time to settle all of this is pre-application. Conditions of approval and development agreements are the tools that work, and they are set before the building permit. When the emergency services assessment, pre-incident planning, training and exercises are written in at that stage, the developer can fund them rather than the county. We cannot promise that every cost shifts, but every dollar the developer carries is a dollar the county keeps. Our checklist on what a county should require before approving a data center covers the broader list.

Frequently asked questions

Do data centers have to report diesel storage to the fire department?

Generally, yes, once diesel on site reaches 10,000 pounds, about 1,430 gallons. Tier II reports are due March 1 each year and go to the state commission, the local emergency planning committee and the fire department.

How long can data center generators run without refueling?

It depends on the design. The Uptime Institute minimum is 12 hours; many large operators plan for 48 to 96 hours with resupply contracts.

Is diesel the main fire risk at a data center?

Diesel is a combustible liquid that is hard to ignite under normal conditions, but a generator yard is a large fire load once a fire starts. Lithium-ion battery rooms are the other major hazard, and the two should be planned together.

When should the fire department get involved?

Before the site plan is filed. Once the layout is approved, changing access, separation or water supply is expensive for everyone.

Planning before the trucks arrive

Data centers can be good neighbors and a strong tax base for the communities that host them. The fuel that keeps them running is a known, manageable hazard when the fire service and the emergency manager have the numbers and a plan before the first tank is set.

ERGSS supports county emergency managers, fire chiefs and data center owners with critical infrastructure planning, pre-incident planning, training and exercises and hazard mitigation. To talk through a project in your jurisdiction, contact us at info@ergss.com or (202) 978-2666.

Joel Yonkman is the founder of ERGSS (Emergency Response & Global Security Solutions). He is a paramedic and emergency manager who served as Planning Section Chief on FEMA Region VI's Incident Management Assistance Team and worked major responses including Deepwater Horizon. More at joelyonkman.com.